Kitchen Timelines

 
       1-7 Days     Week 1     Week 2    Week 3     Week 4   Week 5   Week 6    Week 7   Week 8 

 Planning

  Finalize Plans                
 Order
 Material
      Electrical   Plumbing        Tile
    Arrive 
        Cabinets Arrive    Order 
  Counter
    Top
 
 Demolition      Demolition                
 Framing      Framing              
 Rough-in
 Electric &
 Plumbing
           Rough-in
  Electric &
  Plumbing 
           
 Drywall                  Install
  Drywall
   Prime
         
 Tiling                  Install
  Floor Tile
         Install
  Wall Tile 
 Painting            Painting        
 Cabinets                Install Cabinets    
 Counter Top               Install Counter Top  
 Hardware                 Install Hardware  
 Trim &
 Molding
                    Install Trim &
          Molding
 Turn Key                    Finish
  Project 
This timeline is to be used for planning purposes only.